Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025
Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025
A planned outage of Red Cliffs - Buronga X1 220kV Line in the NSW region was scheduled from 0700 hrs 27/04/2025 to 1700 hrs 02/05/2025.
The outage has been completed and Red Cliffs - Buronga X1 220kV Line returned to service at 1625 hrs 30/04/2025
Constraint set(s) revoked: I-BURC_X1
Manager NEM Real Time Operations
[EventId:202504301045_confirmed] Prices for interval 30-Apr-2025 10:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 30 April 2025
PRICES ARE NOW CONFIRMED for trading interval 30-Apr-2025 10:45.
In accordance with Market Notice 126790 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504301105_confirmed] Prices for interval 30-Apr-2025 11:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 30 April 2025
PRICES ARE NOW CONFIRMED for trading interval 30-Apr-2025 11:05.
In accordance with Market Notice 126794 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504301100_confirmed] Prices for interval 30-Apr-2025 11:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 30 April 2025
PRICES ARE NOW CONFIRMED for trading interval 30-Apr-2025 11:00.
In accordance with Market Notice 126793 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504301055_confirmed] Prices for interval 30-Apr-2025 10:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 30 April 2025
PRICES ARE NOW CONFIRMED for trading interval 30-Apr-2025 10:55.
In accordance with Market Notice 126792 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504301050_confirmed] Prices for interval 30-Apr-2025 10:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 30 April 2025
PRICES ARE NOW CONFIRMED for trading interval 30-Apr-2025 10:50.
In accordance with Market Notice 126791 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504301040_confirmed] Prices for interval 30-Apr-2025 10:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 30 April 2025
PRICES ARE NOW CONFIRMED for trading interval 30-Apr-2025 10:40.
In accordance with Market Notice 126789 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
CHG0102918:Network Change Impacting Norwest and Brisbane Control Room Phone Network
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Network Change Impacting Norwest and Brisbane Control Room Phone Network
Change Start Date & Time: 01/05/2025 11:00:00
Change End Date & Time: 01/05/2025 16:00:00
Outage Start Date & Time: 01/05/2025 12:00:00
Outage End Date & Time: 01/05/2025 15:00:00
Environment: Production
Participant Impact and Requirements: Possibility of experiencing 2 x 30 seconds outages to Norwest and Brisbane Control Room phone networks on 1st May between 12 pm and 2 pm. You are hereby advised to maintain status quo and continue to reach out the Control rooms as you would normally do and only call Norwest on 02 8884 5291 or 02 8884 5292 and Brisbane on 0733473291 or 0733473292 if you have any trouble at all reaching them on their regular operating lines.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Updated Victorian system normal voltage stability limit for the south-west Victoria
Refer to Market Notice 101368
AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.
The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.
Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.
For further details on this constraint equation please contact terry.liu@aemo.com.au
Terry Liu
AEMO Operations