[EventId:202504042015_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 20:15
Issued by Australian Energy Market Operator Ltd at 2015 hrs on 4 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Refer to market notice: 126310
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2015 hrs on 4 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504041915_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 19:15
Issued by Australian Energy Market Operator Ltd at 1915 hrs on 4 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1915 hrs on 4 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504041830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Refer to market notice: 126297
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 4 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504041705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 4 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 4 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:
3/04/2025
7/04/2025
8/04/2025
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:
3/04/2025
7/04/2025
8/04/2025
During the window,FPP calculations may be delayed at various points.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Update - Non-credible contingency event - QLD region - 04/04/2025
Update - Non-credible contingency event - QLD region - 04/04/2025
Refer AEMO Electricity Market Notice 126262
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations
Update - Vulnerable lines in Qld region
Update - Lightning vulnerable lines in Qld region
Refer to AEMO Electricity Market Notice 126262 and 126271
At 0152 hrs 04/04/2025 the the Ross - Townsville South No 7156 and 7249 132kV lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the the Ross - Townsville South No 7156 and 7249 132kV lines to be vulnerable with a category of probable due to lightning.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 04/04/2025
Non-credible contingency event - QLD region - 04/04/2025
At 0152 hrs the Ross - Townsville South No 7156 and 7249 132kV lines tripped and auto reclosed.
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: QLD
Elements: Ross - Townsville South No 7156 and 7249 132kV lines.
Duration: 0152 hrs 04/04/2025 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations