[EventId:202501020800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 January 2025 08:00
Issued by Australian Energy Market Operator Ltd at 0800 hrs on 2 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0800 hrs on 2 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122695 has been updated at 0645 hrs 02/01/2025 to the following:
From 1500 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 103 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1600 hrs 06/01/2025 to 1700 hrs 06/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 509 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
[EventId:202501011630_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 01 January 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 1 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2025.
Refer to market notice: 122668
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1630 hrs on 1 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501011505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 January 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 1 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 1 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 01/01/2025.
Cancellation - Actual MSL1- VIC Region at 1400 hrs 01/01/2025.
Refer to Market Notice 122654 for MSL1.
Manager NEM Real Time Operations
[EventId:202501011400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 01 January 2025 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 1 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2025.
Refer to market notice: 122658
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 1 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501011235_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 01 January 2025 12:35
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 1 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 1 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1235 hrs on 1 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Actual Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Update to Market Notice 122653 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum regional demand is forecast to be 1398 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1535 MW
- MSL2 - 1035 MW
- MSL3 - 535 MW
The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1400 hrs.
Manager NEM Real Time Operations