Market Notices

122109MINIMUM SYSTEM LOAD17/12/2024 03:08:17 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 21/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 21/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1705 MW
o MSL2 - 1205 MW
o MSL3 - 705 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1130 hrs to 1330 hrs 21/12/2024. Minimum regional demand is forecast to be 1643 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
121739INTER-REGIONAL TRANSFER12/12/2024 01:37:40 AM

Inter-Regional Transfer limit variation - Basslink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Basslink

There has been an unplanned outage of the Basslink interconnector.

The following constraint set was invoked at 0130 hrs 12/12/2024

I-BL_ZERO

The constraint set contains the following interconnector on the left hand side.

T-V-MNSP1

Manager NEM Real Time Operations
     
121695INTER-REGIONAL TRANSFER10/12/2024 03:31:22 PM

Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024

AEMO ELECTRICITY MARKET NOTICE
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1, N-Q_MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121688INTER-REGIONAL TRANSFER10/12/2024 01:00:33 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1, N-Q_MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121627INTER-REGIONAL TRANSFER08/12/2024 04:05:37 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_5667C22F from 1600 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121618MINIMUM SYSTEM LOAD08/12/2024 12:40:09 PM

Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL1 - VIC Region at 1230 hrs 08/12/2024.

Refer to Market Notice 121617 for Forecast MSL1.

Manager NEM Real Time Operations
     
121617MINIMUM SYSTEM LOAD08/12/2024 09:57:19 AM

Forecast Minimum System Load MSL1 condition in the VIC Region on 08/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 08/12/2024

Update to Market Notice 121508 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 08/12/2024.

Minimum regional demand is forecast to be 1299 MW at 1300 hrs, and the advisory threshold is:
o MSL1 - 1560 MW
o MSL2 - 1060 MW
o MSL3 - 560 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
From 1130 hrs 08/12/2024 to 1400 hrs 08/12/2024.

Manager NEM Real Time Operations
     
121614INTER-REGIONAL TRANSFER08/12/2024 04:00:08 AM

Inter-regional transfer limit variation - Glenn Innes to Tenterfield 96R 132kV line- NSW region - 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Glenn Innes to Tenterfield 96R 132kV line - NSW region - 08/12/2024

At 0333 hrs 08/12/2024 there was an unplanned outage of Glenn Innes to Tenterfield 96R 132kV line.

The following constraint set(s) invoked at 0345 hrs 08/12/2024
N-96L_96R_CB4102

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
121508MINIMUM SYSTEM LOAD06/12/2024 02:43:31 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm