123555SETTLEMENTS RESIDUE22/01/2025 11:40:30 AM

[EventId:202501221140_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 January 2025 11:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1140 hrs on 22 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.

Refer to market notice: 123553

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1140 hrs on 22 January 2025.

This is an AEMO autogenerated Market Notice.
     
123554INTER-REGIONAL TRANSFER22/01/2025 10:40:43 AM

Inter-regional transfer limit variation -Bundy-Buronga (6F) 330 kV line - NSW region - 21/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - - NSW region - 21/01/2025

At 1935 hrs 21/01/2025 there was a short notice outage of Bundy-Buronga (6F) 330 kV line

The following constraint set(s) invoked
I-BDBU_ONE

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,VIC1-NSW1,V-SA,T-V-MNSP1

The outage is scheduled to return to service at 1935 hrs 22/01/2025

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
123553SETTLEMENTS RESIDUE22/01/2025 10:35:25 AM

[EventId:202501221035_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 January 2025 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 22 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1035 hrs on 22 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123550NON-CONFORMANCE22/01/2025 09:00:31 AM

NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123547NON-CONFORMANCE22/01/2025 06:45:21 AM

NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123535NON-CONFORMANCE21/01/2025 06:40:24 PM

NON-CONFORMANCE Region NSW1 Tuesday, 21 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 21 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 21/01/2025 18:35 to 21/01/2025 18:40
Amount: 44 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123530SETTLEMENTS RESIDUE21/01/2025 04:30:28 PM

[EventId:202501211630_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 January 2025 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 21 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.

Refer to market notice: 123526

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1630 hrs on 21 January 2025.

This is an AEMO autogenerated Market Notice.
     
123526SETTLEMENTS RESIDUE21/01/2025 02:50:21 PM

[EventId:202501211450_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 January 2025 14:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 21 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1450 hrs on 21 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123521NON-CONFORMANCE21/01/2025 01:55:12 PM

NON-CONFORMANCE Region QLD1 Tuesday, 21 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 21 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 21/01/2025 09:45 to 21/01/2025 13:55
Amount: 36 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     