Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/03/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/03/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1354 MW
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 27 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 27 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#1
Duration: 27/02/2025 21:25 to 27/02/2025 21:35
Amount: -11 MW
Constraint: NC-Q_TARONG#1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 27 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 27 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WDBESS1
Duration: 27/02/2025 18:35 to 27/02/2025 18:50
Amount: -55 MW
Constraint: NC-Q_WDBESS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 27 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 27 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 27/02/2025 08:45 to 27/02/2025 08:55
Amount: -7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 26 February 2025
NON-CONFORMANCE NSW1 Region Wednesday, 26 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BERYLSF1
Duration: 26/02/2025 12:15 to 26/02/2025 12:40
Amount: 76 MW
Constraint: NC-N_BERYLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 25 February 2025
NON-CONFORMANCE VIC1 Region Tuesday, 25 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MOKOSF1
Duration: 25/02/2025 09:50 to 25/02/2025 11:00
Amount: 32 MW
Constraint: NC-V_MOKOSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 25 February 2025
NON-CONFORMANCE QLD1 Region Tuesday, 25 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STAN-4
Duration: 25/02/2025 09:30 to 25/02/2025 10:20
Amount: -18 MW
Constraint: NC-Q_STAN-4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 21 February 2025
NON-CONFORMANCE VIC1 Region Friday, 21 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MCKAY1
Duration: 21/02/2025 12:00 to 21/02/2025 12:10
Amount: -54 MW
Constraint: NC-V_MCKAY1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 21 February 2025
NON-CONFORMANCE SA1 Region Friday, 21 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 21/02/2025 11:50 to 21/02/2025 12:05
Amount: -19 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations