122052RECLASSIFY CONTINGENCY16/12/2024 07:24:20 PM

Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Cancellation time: 16/12/2024 19:24

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 122023

Auto-generated on behalf of Manager NEM Real Time Operations
     
122051RECLASSIFY CONTINGENCY16/12/2024 07:04:21 PM

Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Cancellation time: 16/12/2024 19:04

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 122021

Auto-generated on behalf of Manager NEM Real Time Operations
     
122049RESERVE NOTICE16/12/2024 06:40:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.122029 is cancelled at 1835 hrs 16/12/2024.

Manager NEM Real Time Operations
     
122048RECLASSIFY CONTINGENCY16/12/2024 06:21:21 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 16/12/2024 18:21 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
122045RECLASSIFY CONTINGENCY16/12/2024 05:56:25 PM

Reclassification of a Non-Credible Contingency Event: Gordon - Chapel St No 1 220kV line and Gordon - Chapel St No 2 220kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Gordon - Chapel St No 1 220kV and Gordon - Chapel St No 2 220kV

Duration: 16/12/2024 17:56 until further notice

Constraint set(s) invoked:
F-T-CSGO Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-CSGO_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
122044PRICES UNCHANGED16/12/2024 05:50:21 PM

[EventId:202412161725_confirmed] Prices for interval 16-Dec-2024 17:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:25.

In accordance with Market Notice 122030 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122043PRICES UNCHANGED16/12/2024 05:49:11 PM

[EventId:202412161745_confirmed] Prices for interval 16-Dec-2024 17:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:45.

In accordance with Market Notice 122038 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122042PRICES UNCHANGED16/12/2024 05:48:05 PM

[EventId:202412161740_confirmed] Prices for interval 16-Dec-2024 17:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:40.

In accordance with Market Notice 122035 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122041PRICES UNCHANGED16/12/2024 05:46:50 PM

[EventId:202412161735_confirmed] Prices for interval 16-Dec-2024 17:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024

PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:35.

In accordance with Market Notice 122033 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.