Market Notices

124437MINIMUM SYSTEM LOAD10/02/2025 03:30:40 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


AEMO Operations
     
124428PRICES SUBJECT TO REVIEW10/02/2025 12:50:26 PM

[EventId:202502101255_review] Prices for interval 10-Feb-2025 12:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1250 hrs on 10 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124427PRICES SUBJECT TO REVIEW10/02/2025 12:45:30 PM

[EventId:202502101250_review] Prices for interval 10-Feb-2025 12:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1245 hrs on 10 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124425PRICES SUBJECT TO REVIEW10/02/2025 12:40:22 PM

[EventId:202502101245_review] Prices for interval 10-Feb-2025 12:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1240 hrs on 10 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124424PRICES SUBJECT TO REVIEW10/02/2025 12:35:22 PM

[EventId:202502101240_review] Prices for interval 10-Feb-2025 12:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1235 hrs on 10 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124423PRICES SUBJECT TO REVIEW10/02/2025 12:30:24 PM

[EventId:202502101235_review] Prices for interval 10-Feb-2025 12:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 10 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124422PRICES SUBJECT TO REVIEW10/02/2025 12:25:27 PM

[EventId:202502101230_review] Prices for interval 10-Feb-2025 12:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1225 hrs on 10 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Feb-2025 12:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124418MARKET SYSTEMS10/02/2025 11:43:25 AM

INC0140978 - ALERT - Frequency Performance Payments (FPP) System

AEMO ELECTRICITY MARKET NOTICE

ALERT - Frequency Performance Payments (FPP) System

AEMO experienced service interruption relating to Frequency Performance Payments (FPP) System. The FPP System was unable to calculate & publish Contribution Factors (CFs) from 14:36 Hrs AEST on 9/02/2025 till 09:34 Hrs AEST on 10/02/2025.

The service interruption relating to Frequency Performance Payments (FPP) System has now been resolved.

Default Contribution Factors (DCFs) will be applicable for the trading intervals where CFs were not calculated.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
     
124349PRICES SUBJECT TO REVIEW08/02/2025 01:35:23 PM

[EventId:202502081340_review] Prices for interval 08-Feb-2025 13:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 8 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 13:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm