125555POWER SYSTEM EVENTS12/03/2025 12:58:00 PM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125554

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Sheffield George Town No. 1 220kV Line and Sheffield George Town No. 2 220kV Line
Duration: 1300 hrs 12/03/2025 until further notice
Constraint set(s) invoked: T-GTSH_N-2

Manager NEM Real Time Operations
     
125554POWER SYSTEM EVENTS12/03/2025 12:24:04 PM

Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/03/2025

At 1158 hrs the Sheffield George Town No. 1 220kV Line and the Sheffield George Town No. 2 220kV Line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125550POWER SYSTEM EVENTS12/03/2025 09:47:07 AM

Update - Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 12/03/2025

Refer AEMO Electricity Market Notice 125548

At 09:29 hrs the Burnie - Smithton Tee Port Latta No. 1 110kV Line and the Burnie - Smithton Tee Port Latta No. 2 110kV Line tripped and auto-reclosed (2nd event).

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Burnie - Smithton Tee Port Latta No. 1 110kV Line and Burnie - Smithton Tee Port Latta No. 2 110kV Line
Duration: 0940 hrs 12/03/2025 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
125548POWER SYSTEM EVENTS12/03/2025 09:46:32 AM

Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/03/2025

At 0909 hrs the Burnie -Smithton Tee Port Latta No. 1 110kV Line and the Burnie -Smithton Tee Port Latta No. 2 110kV Line tripped and auto-reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125521NON-CONFORMANCE11/03/2025 11:55:21 AM

NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125517POWER SYSTEM EVENTS11/03/2025 10:05:23 AM

Non-credible contingency event - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/03/2025

At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.

AEMO did not instruct load shedding.

Approximately 3 MW of electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
125507PRICES SUBJECT TO REVIEW11/03/2025 08:15:17 AM

[EventId:202503110820_review] Prices for interval 11-Mar-2025 08:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0815 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125506PRICES SUBJECT TO REVIEW11/03/2025 08:10:17 AM

[EventId:202503110815_review] Prices for interval 11-Mar-2025 08:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0810 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125505PRICES SUBJECT TO REVIEW11/03/2025 08:05:18 AM

[EventId:202503110810_review] Prices for interval 11-Mar-2025 08:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0805 hrs on 11 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 11-Mar-2025 08:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     