Market Notices

125268POWER SYSTEM EVENTS05/03/2025 11:57:45 AM

Non-credible contingency event - NSW region - 05/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 05/03/2025

At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line and the Directlink DC1 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125267INTER-REGIONAL TRANSFER05/03/2025 10:51:27 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1040 hrs 05/03/2025

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
125240PRICES SUBJECT TO REVIEW04/03/2025 10:35:18 AM

[EventId:202503041040_review] Prices for interval 04-Mar-2025 10:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125238PRICES SUBJECT TO REVIEW04/03/2025 10:30:17 AM

[EventId:202503041035_review] Prices for interval 04-Mar-2025 10:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1030 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125236PRICES SUBJECT TO REVIEW04/03/2025 10:25:24 AM

[EventId:202503041030_review] Prices for interval 04-Mar-2025 10:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1025 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125235PRICES SUBJECT TO REVIEW04/03/2025 10:20:20 AM

[EventId:202503041025_review] Prices for interval 04-Mar-2025 10:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125234PRICES SUBJECT TO REVIEW04/03/2025 10:15:20 AM

[EventId:202503041020_review] Prices for interval 04-Mar-2025 10:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1015 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125233PRICES SUBJECT TO REVIEW04/03/2025 10:10:21 AM

[EventId:202503041015_review] Prices for interval 04-Mar-2025 10:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125232PRICES SUBJECT TO REVIEW04/03/2025 10:05:18 AM

[EventId:202503041010_review] Prices for interval 04-Mar-2025 10:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 4 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Mar-2025 10:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     