Network Augmentation Commissioned - QLD Region - 13/02/2025
Network Augmentation Commissioned - QLD Region - 13/02/2025
Commissioned:
Larcom Creek - Aldoga SF 8994 275kV line.
Manager NEM Real Time Operations
[EventId:202502141705_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 14 February 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1705 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0100546 - Production eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release
Change Start Date & Time: 23/02/2025 10:00:00
Change End Date & Time: 23/02/2025 17:00:00
Outage Start Date & Time: 23/02/2025 10:00:00
Outage End Date & Time: 23/02/2025 14:00:00
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market
Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Start Date & Time: 18/02/2025 09:00:00
Change End Date & Time: 18/02/2025 21:00:00
Outage Start Date & Time: 18/02/2025 18:30:00
Outage End Date & Time: 18/02/2025 20:30:00
Environment: Production
Participant Impact and Requirements: DWGM market system (Webexchanger and MIBB) outage due to planned maintenance.
The following impacts are expected during the maintenance activities:
- All access to the Declared Wholesale Gas Market Production Systems will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
[EventId:202502141235_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 February 2025 12:35
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 14 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 February 2025.
Refer to market notice: 124657
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1235 hrs on 14 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502141200_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 14 February 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 14 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Refer to market notice: 124656
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1200 hrs on 14 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502141050_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 February 2025 10:50
Issued by Australian Energy Market Operator Ltd at 1050 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1050 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502141015_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 14 February 2025 10:15
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 14 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1015 hrs on 14 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502141000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 14 February 2025 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 14 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 14 February 2025.
Refer to market notice: 124653
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1000 hrs on 14 February 2025.