[EventId:202504072000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 April 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 7 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 April 2025.
Refer to market notice: 126420
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2000 hrs on 7 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504071700_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 April 2025 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 7 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1700 hrs on 7 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Create Market Notice - Inital - CHG0102537 - NOR Pre-Prod GFRC will have scheduled maintenance works outage from 9.00am Wednesday 9 April until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Windows Server
Change Title: NOR Pre-Prod GFRC will have scheduled maintenance works outage from 9.00am Wednesday 9 April until 12pm (EST)
Change Start Date & Time: 09/04/2025 09:00:00
Change End Date & Time: 09/04/2025 12:00:00
Outage Start Date & Time: 09/04/2025 09:00:00
Outage End Date & Time: 09/04/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
[EventId:202504062030_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 06 April 2025 20:30
Issued by Australian Energy Market Operator Ltd at 2030 hrs on 6 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 April 2025.
Refer to market notice: 126390
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2030 hrs on 6 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504061750_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 April 2025 17:50
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 6 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1750 hrs on 6 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504042015_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 20:15
Issued by Australian Energy Market Operator Ltd at 2015 hrs on 4 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Refer to market notice: 126310
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2015 hrs on 4 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504041915_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 19:15
Issued by Australian Energy Market Operator Ltd at 1915 hrs on 4 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1915 hrs on 4 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504041830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Refer to market notice: 126297
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 4 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504041705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 4 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 4 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.