126873MARKET INTERVENTION05/05/2025 03:57:30 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126854

TORRB2 TORRENS ISLAN at 2300 hrs 02/05/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/05/2025.

The direction update is issued at 1600 hrs 05/05/2025.

Manager NEM Real Time Operations
     
126872MARKET INTERVENTION05/05/2025 03:57:30 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126855

PPCCGT PELICAN POINT at 0001 hrs 03/05/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 0400 hrs 07/05/2025.

The direction update is issued at 1600 hrs 05/05/2025.

Manager NEM Real Time Operations
     
126871INTER-REGIONAL TRANSFER05/05/2025 01:52:26 PM

Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Mudgeeraba No. 836 275 kV Line - QLD region - 05/05/2025

At 1336 hrs 05/05/2025 there was an unplanned outage of Greenbank - Mudgeeraba No. 836 275 kV Line.

The following constraint set(s) invoked at 1340 hrs 05/05/2025
Q-GBMU_835_836

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126855MARKET INTERVENTION04/05/2025 03:00:14 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126852

PPCCGT PELICAN POINT at 0001 hrs 03/05/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 0400 hrs 06/05/2025.

The direction update is issued at 1500 hrs 04/05/2025.

Manager NEM Real Time Operations
     
126854MARKET INTERVENTION04/05/2025 02:58:28 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126851

TORRB2 TORRENS ISLAN at 2300 hrs 02/05/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 06/05/2025.

The direction update is issued at 1500 hrs 04/05/2025.

Manager NEM Real Time Operations
     
126853INTER-REGIONAL TRANSFER03/05/2025 04:11:50 PM

Inter-regional transfer limit variation - South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -South Morang - Thomastown No 2 220 kV Line - VIC region - 03/05/2025

A planned outage of South Morang - Thomastown No 2 220 kV Line in the VIC region was scheduled from 0629 hrs 03/05/2025 to 1830 hrs 03/05/2025.

The outage has been completed and South Morang - Thomastown No 2 220 kV Line returned to service at 1615 hrs 03/05/2025

Constraint set(s) revoked: V-SMTT2

Manager NEM Real Time Operations
     
126852MARKET INTERVENTION03/05/2025 03:05:44 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126850

PPCCGT PELICAN POINT at 0001 hrs 03/05/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 0400 hrs 05/05/2025.

The direction update is issued at 1500 hrs 03/05/2025.

Manager NEM Real Time Operations
     
126851MARKET INTERVENTION03/05/2025 03:03:44 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126849

TORRB2 TORRENS ISLAN at 2300 hrs 02/05/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/05/2025.

The direction update is issued at 1500 hrs 03/05/2025.

Manager NEM Real Time Operations
     
126850MARKET INTERVENTION02/05/2025 04:00:18 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126848


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 02/05/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0000 hrs 03/05/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 04/05/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.