Market Notices

126301PRICES SUBJECT TO REVIEW04/04/2025 05:20:12 PM

[EventId:202504041725_review] Prices for interval 04-Apr-2025 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 4 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Apr-2025 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126300PRICES SUBJECT TO REVIEW04/04/2025 05:15:16 PM

[EventId:202504041720_review] Prices for interval 04-Apr-2025 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 4 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Apr-2025 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126299PRICES SUBJECT TO REVIEW04/04/2025 05:10:16 PM

[EventId:202504041715_review] Prices for interval 04-Apr-2025 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 4 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Apr-2025 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126298PRICES SUBJECT TO REVIEW04/04/2025 05:05:18 PM

[EventId:202504041710_review] Prices for interval 04-Apr-2025 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 4 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Apr-2025 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126296PRICES SUBJECT TO REVIEW04/04/2025 05:00:26 PM

[EventId:202504041705_review] Prices for interval 04-Apr-2025 17:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 4 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Apr-2025 17:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126294PRICES SUBJECT TO REVIEW04/04/2025 04:55:21 PM

[EventId:202504041700_review] Prices for interval 04-Apr-2025 17:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 4 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Apr-2025 17:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126291MARKET SYSTEMS04/04/2025 03:33:34 PM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025


During the window,FPP calculations may be delayed at various points.


Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126281NON-CONFORMANCE04/04/2025 01:15:15 PM

NON-CONFORMANCE Region SA1 Friday, 4 April 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 4 April 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ADPBA1
Duration: 04/04/2025 12:30 to 04/04/2025 13:15
Amount: -6 MW
Constraint: NC-S_ADPBA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126275MARKET SYSTEMS04/04/2025 09:23:36 AM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00

Environment: Pre-Production

Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025

During the window,FPP calculations may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm