Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126487 is cancelled at 1910 hrs 10/04/2025.
Manager NEM Real Time Operations
[EventId:202504101900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 April 2025 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 10 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.
Refer to market notice: 126477
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 10 April 2025.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1585 MW
The minimum capacity reserve available is 1337 MW
Manager NEM Real Time Operations
[EventId:202504101705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 April 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 10 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126467 is cancelled at 1540 hrs 10/04/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 10 April 2025
NON-CONFORMANCE NSW1 Region Thursday, 10 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: QBYNB1
Duration: 10/04/2025 15:25 to 10/04/2025 15:35
Amount: -9 MW
Constraint: NC-N_QBYNB1
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1595 MW.
The minimum capacity reserve available is 1577 MW.
Manager NEM Real Time Operations
[EventId:202504091915_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 April 2025 19:15
Issued by Australian Energy Market Operator Ltd at 1915 hrs on 9 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 April 2025.
Refer to market notice: 126459
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1915 hrs on 9 April 2025.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Wednesday, 9 April 2025
NON-CONFORMANCE NSW1 Region Wednesday, 9 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 09/04/2025 19:00 to 09/04/2025 19:05
Amount: -38 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations