CHG0101145 | Production | Planned Maintenance to Norwest Internet Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet Router
Change Start Date & Time: 15/02/2025 10:00:00 AEST
Change End Date & Time: 15/02/2025 15:00:00 AEST
Outage Start Date & Time: 15/02/2025 11:00:00 AEST
Outage End Date & Time: 15/02/2025 13:00:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.
B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO NSW Datacentre if VPN connection is only terminating in NSW only.
SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.
GASHUB: Nil
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point 202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) prior to this scheduled outage.
*** Failure to do so will impact connectivity to Marketnet Services. ***
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region NSW1 Friday, 7 February 2025
NON-CONFORMANCE NSW1 Region Friday, 7 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 07/02/2025 03:40 to 07/02/2025 03:50
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502061735_review] Prices for interval 06-Feb-2025 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 6 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2025 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502061730_review] Prices for interval 06-Feb-2025 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 6 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2025 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502061725_review] Prices for interval 06-Feb-2025 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 6 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2025 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502061720_review] Prices for interval 06-Feb-2025 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 6 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2025 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502061715_review] Prices for interval 06-Feb-2025 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 6 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2025 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502061710_review] Prices for interval 06-Feb-2025 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 6 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2025 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Thursday, 6 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 6 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: KINGASF1
Duration: 06/02/2025 14:55 to 06/02/2025 16:15
Amount: 29 MW
Constraint: NC-Q_KINGASF1
Auto-generated on behalf of Manager NEM Real Time Operations