Update - Non-credible contingency event - NSW region - 07/03/2025
Update - Non-credible contingency event - NSW region - 07/03/2025
Refer AEMO Electricity Market Notice 125536
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will no longer reclassify this event as a credible contingency event.
Region: NSW
Elements:
- Lismore132 - Mullumbimby 9U6 132kV Line
- Lismore132 - Mullumbimby 9U7 132kV Line
- Ewingsdale - Mullumbimby 9G5 132kV Line
Duration: 1730 hrs 11/03/2025 until 1230 hrs 27/05/2025
Constraint set(s) invoked: NONE
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/05/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127067 is cancelled at 1410 hrs 15/05/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 16/05/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 16/05/2025 to 1800 hrs 16/05/2025.
The forecast capacity reserve requirement is 1216 MW.
The minimum capacity reserve available is 1201 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/05/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127043 is cancelled at 1740 hrs 13/05/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/05/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 13/05/2025 to 1800 hrs 13/05/2025.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 1070 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/05/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127025 is cancelled at 1645 hrs 13/05/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/05/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 14/05/2025 to 1800 hrs 14/05/2025.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 1366 MW.
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 20/05/2025
Network Augmentation Commissioned - NSW Region - 20/05/2025
At 1700 hrs 20/05/2025, the Buronga No.5 330kV synchronous condenser has been commissioned.
Manager NEM Real Time Operations
Network Augmentation Commissioned - Vic Region - 29/04/2025
Network Augmentation Commissioned - Vic Region - 29/04/2025
At 2030hrs 29/04/2025, the existing Haunted Gully - Tarrone No1 500 kV transmission line has been cut in at Mortlake Power Station to create the following transmission line sections:
Mortlake PS - Tarrone No.1 500 kV transmission line
Mortlake PS - Haunted Gully No.1 500 kV transmission line
Manager NEM Real Time Operations