NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025
NON-CONFORMANCE NSW1 Region Wednesday, 5 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 05/02/2025 23:15 to 06/02/2025 00:25
Amount: -20 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502051800_review] Prices for interval 05-Feb-2025 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051755_review] Prices for interval 05-Feb-2025 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051750_review] Prices for interval 05-Feb-2025 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051745_review] Prices for interval 05-Feb-2025 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051740_review] Prices for interval 05-Feb-2025 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502051735_review] Prices for interval 05-Feb-2025 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124044
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations
[EventId:202502051320_review] Prices for interval 05-Feb-2025 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 5 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.