Market Notices

123439MARKET INTERVENTION18/01/2025 08:10:48 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 123438

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 19/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1230 hrs 18/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
123438MARKET INTERVENTION18/01/2025 07:46:08 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 19/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123418SETTLEMENTS RESIDUE17/01/2025 06:00:29 PM

[EventId:202501171800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 January 2025 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 17 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Refer to market notice: 123415

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 17 January 2025.

This is an AEMO autogenerated Market Notice.
     
123415SETTLEMENTS RESIDUE17/01/2025 04:05:34 PM

[EventId:202501171605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 January 2025 16:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 17 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123413SETTLEMENTS RESIDUE17/01/2025 03:31:26 PM

[EventId:202501171530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 January 2025 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 17 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Refer to market notice: 123405

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 17 January 2025.

This is an AEMO autogenerated Market Notice.
     
123408MARKET INTERVENTION17/01/2025 02:52:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123385

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123407MARKET INTERVENTION17/01/2025 02:50:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123384

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123406POWER SYSTEM EVENTS17/01/2025 02:46:41 PM

Update Non-credible contingency event - NSW region - 17/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update Non-credible contingency event - NSW region - 17/01/2025

Refer AEMO Electricity Market Notice 123404

At 0825 hrs the Buronga 330 kV B Bus tripped.
AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
123405SETTLEMENTS RESIDUE17/01/2025 01:10:24 PM

[EventId:202501171310_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 January 2025 13:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 17 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1310 hrs on 17 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     