Filter by category
Filter by Date
[EventId:202412221800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2024 18:00
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Refer to market notice: 122412
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 22 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412221605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2024 16:05
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 22 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 22 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 22/12/2024.
Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 22/12/2024.
Cancellation - Actual MSL1- VIC Region at 1430 hrs 22/12/2024.
Refer to Market Notice 122399for MSL1.
Manager NEM Real Time Operations
Actual Minimum System Load MSL1 condition in the VIC Region on 22/12/2024
Actual Minimum System Load MSL1 condition in the VIC Region on 22/12/2024
Update to Market Notice 122377 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.
Minimum regional demand is forecast to be 1409 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1760 MW
- MSL2 - 1260 MW
- MSL3 - 760 MW
The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1430 hrs.
Manager NEM Real Time Operations
[EventId:202412221020_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2024 10:20
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 22 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Refer to market notice: 122392
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1020 hrs on 22 December 2024.
This is an AEMO autogenerated Market Notice.
Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.
Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.
Cancellation - Forecast MSL2- VIC Region at 1015 hrs 22/12/2024.
Refer to Market Notice 122385 for MSL2.
Manager NEM Real Time Operations
[EventId:202412220740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2024 07:40
Issued by Australian Energy Market Operator Ltd at 0740 hrs on 22 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0740 hrs on 22 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024
Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1790 MW
- MSL2 - 1290 MW
- MSL3 - 790 MW
The regional demand is forecast to be below the MSL2 threshold for the following period[s]:
- From 1200 hrs 22/12/2024 to 1330 hrs 22/12/2024. Minimum regional demand is forecast to be 1219 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations
[EventId:202412211700_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 21 December 2024 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 21 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2024.
Refer to market notice: 122375
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1700 hrs on 21 December 2024.
This is an AEMO autogenerated Market Notice.