Market Notices

125990INTER-REGIONAL TRANSFER27/03/2025 08:27:19 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 27/03/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_56F70932 from 0820 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Manager NEM Real Time Operations
     
125964INTER-REGIONAL TRANSFER26/03/2025 04:39:26 PM

Inter-regional transfer limit variation - Palmerston A 220kV Bus - TAS region - 26/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Palmerston A 220kV Bus - TAS region - 26/03/2025

Refer to Market Notice 125962.

The following constraint set(s) invoked from 1600 hrs to 1620 hrs 26/03/2026.
T-LIPM_WACB
T-LIPM_WACB_SL_N-2


This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125945INTER-REGIONAL TRANSFER25/03/2025 03:53:45 PM

Inter-regional transfer limit variation - Lower Tumut - Canberra 07 330kV Line - NSW region - 25/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lower Tumut - Canberra 07 330kV Line - NSW region - 25/03/2025

A planned outage of Lower Tumut - Canberra 07 330kV Line in the NSW region was scheduled from 1746 hrs 21/03/2025 to 1800 hrs 26/03/2025.

The outage has been completed and Lower Tumut - Canberra 07 330kV Line returned to service at 1555 hrs 25/03/2025

Constraint set(s) revoked: N-CNLT_07

Manager NEM Real Time Operations
     
125835INTER-REGIONAL TRANSFER21/03/2025 06:07:23 PM

Inter-regional transfer limit variation - Canberra - Lower Tumut (07) 330 kV Line. - NSW region - 21/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Canberra - Lower Tumut (07) 330 kV Line - NSW region - 21/03/2025

At 1746 hrs 21/03/2025 there was an unplanned outage of Canberra - Lower Tumut (07) 330 kV Line.

The following constraint sets invoked at 1800 hrs 21/03/2025
N-CNLT_07
N-X_4+07_WG_CLOSE

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW-QLD1
VIC-NSW1
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125826INTER-REGIONAL TRANSFER21/03/2025 12:21:33 PM

Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Darlington Point - Balranald X5 220kV Line - NSW region - 21/03/2025

A planned outage of Darlington Point - Balranald X5 220kV Line in the NSW region was scheduled from 0600 hrs 21/03/2025 to 1600 hrs 21/03/2025.

The outage has been completed and Darlington Point - Balranald X5 220kV Line returned to service at 1220 hrs 21/03/2025

Constraint set(s) revoked: N-BADP

Manager NEM Real Time Operations
     
125788INTER-REGIONAL TRANSFER19/03/2025 03:12:44 PM

Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Robertstown - Tungkillo 1 275 kV line - SA region - 19/03/2025

At 1450 hrs 19/03/2025 there was a short notice outage of Robertstown - Tungkillo 1 275 kV line.

The following constraint set(s) invoked at 1455 hrs 19/03/2025
S-RBTU

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125647INTER-REGIONAL TRANSFER14/03/2025 05:11:12 PM

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.

The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     