[EventId:202503060740_review] Prices for interval 06-Mar-2025 07:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 6 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 07:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503060735_review] Prices for interval 06-Mar-2025 07:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0730 hrs on 6 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Mar-2025 07:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503051825_review] Prices for interval 05-Mar-2025 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 5 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Mar-2025 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503051820_review] Prices for interval 05-Mar-2025 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 5 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Mar-2025 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503051815_review] Prices for interval 05-Mar-2025 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 5 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Mar-2025 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503051810_review] Prices for interval 05-Mar-2025 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 5 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Mar-2025 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503051805_review] Prices for interval 05-Mar-2025 18:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Mar-2025 18:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202503051800_review] Prices for interval 05-Mar-2025 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 5 March 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 05-Mar-2025 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 05/03/2025
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/03/2025 to 1600 hrs 06/03/2025.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1635 hrs 05/03/2025
Constraint set(s) revoked: N-LDTM_82
Manager NEM Real Time Operations