126786CONSTRAINTS29/04/2025 05:43:58 PM

Updated Victorian system normal voltage stability limit for the south-west Victoria

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 101368

AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.

The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.

Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.

For further details on this constraint equation please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
     
126762PRICES SUBJECT TO REVIEW27/04/2025 02:50:26 PM

[EventId:202504271455_review] Prices for interval 27-Apr-2025 14:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126759PRICES SUBJECT TO REVIEW27/04/2025 02:45:15 PM

[EventId:202504271450_review] Prices for interval 27-Apr-2025 14:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126758PRICES SUBJECT TO REVIEW27/04/2025 02:40:13 PM

[EventId:202504271445_review] Prices for interval 27-Apr-2025 14:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126757PRICES SUBJECT TO REVIEW27/04/2025 02:35:22 PM

[EventId:202504271440_review] Prices for interval 27-Apr-2025 14:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126756PRICES SUBJECT TO REVIEW27/04/2025 02:30:11 PM

[EventId:202504271435_review] Prices for interval 27-Apr-2025 14:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126755PRICES SUBJECT TO REVIEW27/04/2025 02:25:10 PM

[EventId:202504271430_review] Prices for interval 27-Apr-2025 14:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1425 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126754PRICES SUBJECT TO REVIEW27/04/2025 02:20:17 PM

[EventId:202504271425_review] Prices for interval 27-Apr-2025 14:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1420 hrs on 27 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Apr-2025 14:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126701PRICES SUBJECT TO REVIEW23/04/2025 02:55:11 PM

[EventId:202504231500_review] Prices for interval 23-Apr-2025 15:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1455 hrs on 23 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 23-Apr-2025 15:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     