Market Notices

122490MINIMUM SYSTEM LOAD26/12/2024 02:41:29 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025

Update to Market Notice 122466 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1660 MW
- MSL2 - 1160 MW
- MSL3 - 660 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 01/01/2025 to 1330 hrs 01/01/2025. Minimum regional demand is forecast to be 1474 MW at 1300 hrs.


Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
122489MINIMUM SYSTEM LOAD26/12/2024 02:39:52 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 29/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 29/12/2024

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 29/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1730 MW
- MSL2 - 1230 MW
- MSL3 - 730 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1100 hrs 29/12/2024 to 1400 hrs 29/12/2024. Minimum regional demand is forecast to be 1489 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

Manager NEM Real Time Operations
     
122487INTER-REGIONAL TRANSFER26/12/2024 08:50:33 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of all of Directlink.

The following constraint set was invoked at 0840 hrs 26/12/2024

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
122480PRICES SUBJECT TO REVIEW25/12/2024 05:25:20 PM

[EventId:202412251730_review] Prices for interval 25-Dec-2024 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 25 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122479PRICES SUBJECT TO REVIEW25/12/2024 05:20:14 PM

[EventId:202412251725_review] Prices for interval 25-Dec-2024 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 25 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122478PRICES SUBJECT TO REVIEW25/12/2024 05:15:12 PM

[EventId:202412251720_review] Prices for interval 25-Dec-2024 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 25 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122477PRICES SUBJECT TO REVIEW25/12/2024 05:10:20 PM

[EventId:202412251715_review] Prices for interval 25-Dec-2024 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 25 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122476PRICES SUBJECT TO REVIEW25/12/2024 05:05:19 PM

[EventId:202412251710_review] Prices for interval 25-Dec-2024 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 25 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122475PRICES SUBJECT TO REVIEW25/12/2024 05:00:33 PM

[EventId:202412251705_review] Prices for interval 25-Dec-2024 17:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 25 December 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Dec-2024 17:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     