124075PRICES SUBJECT TO REVIEW04/02/2025 01:47:11 PM

[EventId:202502041325_review] Prices for interval 04-Feb-2025 13:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1320 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124073PRICES SUBJECT TO REVIEW04/02/2025 01:34:53 PM

[EventId:202502041320_review] Prices for interval 04-Feb-2025 13:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1315 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124071PRICES SUBJECT TO REVIEW04/02/2025 01:41:00 PM

[EventId:202502041315_review] Prices for interval 04-Feb-2025 13:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124070PRICES SUBJECT TO REVIEW04/02/2025 01:28:35 PM

[EventId:202502041310_review] Prices for interval 04-Feb-2025 13:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124068PRICES SUBJECT TO REVIEW04/02/2025 01:10:06 PM

[EventId:202502041305_review] Prices for interval 04-Feb-2025 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 4 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Feb-2025 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
124065NON-CONFORMANCE04/02/2025 12:15:15 PM

NON-CONFORMANCE Region NSW1 Tuesday, 4 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 4 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 04/02/2025 12:05 to 04/02/2025 12:15
Amount: -57 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124044POWER SYSTEM EVENTS03/02/2025 02:13:15 PM

Update - Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 03/02/2025

Refer AEMO Electricity Market Notice 124043

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.

Region: TAS

Elements: Farrell - Reece No.1 and No.2 220 kV lines
Duration: 1410 hrs 03/02/2025 until further notice
Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
124043POWER SYSTEM EVENTS03/02/2025 02:02:24 PM

Non-credible contingency event - TAS region - 03/02/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 03/02/2025

At 1333 hrs the Farrell - Reece No.1 and No.2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
124041NON-CONFORMANCE03/02/2025 10:46:30 AM

NON-CONFORMANCE Region NSW1 Monday, 3 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 3 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm