123696RECLASSIFY CONTINGENCY24/01/2025 09:50:05 PM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/01/2025 21:50 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
123695RECLASSIFY CONTINGENCY24/01/2025 09:50:01 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 24/01/2025 21:49 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
123694RESERVE NOTICE24/01/2025 07:11:31 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 123693 is cancelled at 1910 hrs 24/01/2025.

Manager NEM Real Time Operations
     
123693RESERVE NOTICE24/01/2025 06:16:38 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 24/01/2025 to 1900 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 816 MW.


Manager NEM Real Time Operations
     
123690PRICES UNCHANGED24/01/2025 05:06:15 PM

[EventId:202501241640_confirmed] Prices for interval 24-Jan-2025 16:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 24 January 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 16:40.

In accordance with Market Notice 123679 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123689PRICES UNCHANGED24/01/2025 05:04:57 PM

[EventId:202501241700_confirmed] Prices for interval 24-Jan-2025 17:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 24 January 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 17:00.

In accordance with Market Notice 123684 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123688PRICES UNCHANGED24/01/2025 05:03:44 PM

[EventId:202501241655_confirmed] Prices for interval 24-Jan-2025 16:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 24 January 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 16:55.

In accordance with Market Notice 123683 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123687PRICES UNCHANGED24/01/2025 05:07:25 PM

[EventId:202501241650_confirmed] Prices for interval 24-Jan-2025 16:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 24 January 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 16:50.

In accordance with Market Notice 123681 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123686PRICES UNCHANGED24/01/2025 05:00:22 PM

[EventId:202501241645_confirmed] Prices for interval 24-Jan-2025 16:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 24 January 2025

PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 16:45.

In accordance with Market Notice 123680 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     