PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122118 is cancelled at 1920 hrs 17/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1830 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1662 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 18th December 2024 0700-2200 for flows in both directions up to 150 MW
Refer to market notice 120706
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 150 MW on 18th December from 07:00hrs to 22:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122096 has been updated to the following:
[1.] From 1600 hrs 17/12/2024 to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 996 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122071 has been updated to the following:
[1.] From 1530 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 815 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122007 has been updated to the following:
[1.] From 1430 hrs 17/12/2024 to 1530 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 907 MW.
[2.] From 1800 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1012 MW.
Manager NEM Real Time Operations
[EventId:202412161725_confirmed] Prices for interval 16-Dec-2024 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:25.
In accordance with Market Notice 122030 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161745_confirmed] Prices for interval 16-Dec-2024 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:45.
In accordance with Market Notice 122038 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161740_confirmed] Prices for interval 16-Dec-2024 17:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:40.
In accordance with Market Notice 122035 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.