Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 122272
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 20/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 19/12/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 20/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 16/12/2024
Cancellation - AEMO Intervention Event - SA region 16/12/2024
Refer to Market Notice 122011
The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 19/12/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122198
Direction is cancelled from: 1530 hrs 19/12/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122199
Direction is cancelled from: 1500 hrs 19/12/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122110
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 19/12/2024.
The direction update is issued at 1600 hrs 18/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122111
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 19/12/2024.
The direction update is issued at 1600 hrs 18/12/2024.
Manager NEM Real Time Operations
Network Augmentation Commissioned - SA Region - 18/12/2024
Network Augmentation Commissioned - SA Region - 18/12/2024
At 0910 hrs 18/12/2024, the Para East Left Bus 275 kV Reactor has been commissioned.
Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 18th December 2024 0700-2200 for flows in both directions up to 150 MW
Refer to market notice 120706
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 150 MW on 18th December from 07:00hrs to 22:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations