Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025
Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025
At 1140 hrs 26/04/2025 there was a short notice outage of Griffith - Yanco 99J 132 kV Line.
The following constraint set(s) invoked at 1140 hrs 26/04/2025
N-GFYC-99J-C
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Release of QNI limit from NSW to Qld - 29th April 2025
Refer to market notice 124749.
AEMO, Transgrid, Powerlink have reviewed the test results following the QNI minor testing on 16th February 2025. The next hold point can now be released.
The hold point of 950 MW from NSW to Qld will be implemented as of 1000 hrs 29th April 2025.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
NON-CONFORMANCE Region SA1 Thursday, 24 April 2025
NON-CONFORMANCE SA1 Region Thursday, 24 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BLYTHB1
Duration: 24/04/2025 13:50 to 24/04/2025 13:55
Amount: 143 MW
Constraint: NC-S_BLYTHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 23 April 2025
NON-CONFORMANCE NSW1 Region Wednesday, 23 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: JEMALNG1
Duration: 23/04/2025 08:50 to 23/04/2025 10:00
Amount: 38 MW
Constraint: NC-N_JEMALNG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 19 April 2025
NON-CONFORMANCE QLD1 Region Saturday, 19 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 19/04/2025 14:20 to 19/04/2025 14:30
Amount: 15 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank - Molendinar 8825 275kV line - QLD region - 16/04/2025
Inter-regional transfer limit variation - Greenbank - Molendinar 8825 275kV line - QLD region - 16/04/2025
At 2110 hrs 16/04/2025 there was an unplanned outage of Greenbank - Molendinar 8825 275kV line.
The following constraint set(s) invoked at 2120 hrs 16/04/2025
Q-GBMO_8824_8825
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector -Yass 3L 330kV Line - NSW region - 14/04/2025
Inter-regional transfer limit variation - Collector -Yass 3L 330kV Line - NSW region - 14/04/2025
A planned outage of the Collector -Yass 3L 330kV Line in the NSW region was scheduled from 0700 hrs 12/04/2025 to 1700 hrs 16/04/2025.
The outage has been completed and the Collector -Yass 3L 330kV Line returned to service at 1735 hrs 14/04/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank SVC- QLD region - 11/04/2025
Inter-regional transfer limit variation - Greenbank SVC - QLD region - 11/04/2025
At 1600 hrs 11/04/2025 there was an unplanned outage of Greenbank SVC.
The following constraint set(s) invoked at 1605 hrs 11/04/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 10 April 2025
NON-CONFORMANCE NSW1 Region Thursday, 10 April 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: QBYNB1
Duration: 10/04/2025 15:25 to 10/04/2025 15:35
Amount: -9 MW
Constraint: NC-N_QBYNB1
Auto-generated on behalf of Manager NEM Real Time Operations