Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Duration: 22/12/2024 13:47 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 22/12/2024 13:29 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 22/12/2024 13:17 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Duration: 22/12/2024 13:04 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Actual Minimum System Load MSL1 condition in the VIC Region on 22/12/2024
Actual Minimum System Load MSL1 condition in the VIC Region on 22/12/2024
Update to Market Notice 122377 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.
Minimum regional demand is forecast to be 1409 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1760 MW
- MSL2 - 1260 MW
- MSL3 - 760 MW
The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1430 hrs.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 22/12/2024 10:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122394
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 22/12/2024 10:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122393
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.
Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.
Cancellation - Forecast MSL2- VIC Region at 1015 hrs 22/12/2024.
Refer to Market Notice 122385 for MSL2.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 22/12/2024 08:33 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations