Market Notices

122800MARKET INTERVENTION03/01/2025 02:37:39 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 122799

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0600 hrs 04/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1500 hrs 03/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
122799MARKET INTERVENTION03/01/2025 02:12:20 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0600 hrs 04/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
122797MARKET INTERVENTION03/01/2025 01:31:43 PM

Cancellation - AEMO Intervention Event - SA region 24/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 24/12/2024

Refer to Market Notice 122451

The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 03/01/2025.


Manager NEM Real Time Operations
     
122795MARKET INTERVENTION03/01/2025 01:05:21 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122755

Direction is cancelled from: 1305 hrs 03/01/2025

Manager NEM Real Time Operations
     
122794MARKET INTERVENTION03/01/2025 01:30:21 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122753

Direction is cancelled from: 1330 hrs 03/01/2025

Manager NEM Real Time Operations
     
122793SETTLEMENTS RESIDUE03/01/2025 11:30:37 AM

[EventId:202501031130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 January 2025 11:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1130 hrs on 3 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 January 2025.

Refer to market notice: 122782

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 3 January 2025.

This is an AEMO autogenerated Market Notice.
     
122791PRICES UNCHANGED03/01/2025 10:03:33 AM

[EventId:202501030940_confirmed] Prices for interval 03-Jan-2025 09:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 3 January 2025

PRICES ARE NOW CONFIRMED for trading interval 03-Jan-2025 09:40.

In accordance with Market Notice 122780 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122790PRICES UNCHANGED03/01/2025 10:07:12 AM

[EventId:202501031000_confirmed] Prices for interval 03-Jan-2025 10:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 3 January 2025

PRICES ARE NOW CONFIRMED for trading interval 03-Jan-2025 10:00.

In accordance with Market Notice 122785 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122789PRICES UNCHANGED03/01/2025 10:02:14 AM

[EventId:202501030955_confirmed] Prices for interval 03-Jan-2025 09:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 3 January 2025

PRICES ARE NOW CONFIRMED for trading interval 03-Jan-2025 09:55.

In accordance with Market Notice 122784 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.