Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 124446
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2100 hrs 10/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1800 hrs 10/02/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2100 hrs 10/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 06/02/2025
Cancellation - AEMO Intervention Event - SA region 06/02/2025
Refer to Market Notice 124253
The AEMO Intervention Event and all associated directions are cancelled from 1730 hrs on 10/02/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124440
Direction is cancelled from: 1710 hrs 10/02/2025
Manager NEM Real Time Operations
[EventId:202502101600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124442
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502101505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 February 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 10 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 10 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 124414
Direction is cancelled from: 1730 hrs 10/02/2025
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 124394
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1030 hrs 11/02/2025.
The direction update is issued at 1530 hrs 10/02/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 10 February 2025
NON-CONFORMANCE NSW1 Region Monday, 10 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2
Auto-generated on behalf of Manager NEM Real Time Operations