122596SETTLEMENTS RESIDUE30/12/2024 04:00:29 PM

[EventId:202412301600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2024 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 30 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.

Refer to market notice: 122589

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 30 December 2024.

This is an AEMO autogenerated Market Notice.
     
122589SETTLEMENTS RESIDUE30/12/2024 02:35:31 PM

[EventId:202412301435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 30 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 30 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122588MINIMUM SYSTEM LOAD30/12/2024 02:56:17 PM

Forecast Minimum System Load MSL1 condition in the VIC region on 01/01/2025

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 122490 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 01/01/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
MSL1 - 1560 MW
MSL2 - 1060 MW
MSL3 - 560 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1430 hrs 01/01/2025. Minimum regional demand is forecast to be 1264 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.


AEMO Operations
     
122585SETTLEMENTS RESIDUE30/12/2024 01:30:31 PM

[EventId:202412301330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 30 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.

Refer to market notice: 122579

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 30 December 2024.

This is an AEMO autogenerated Market Notice.
     
122579SETTLEMENTS RESIDUE30/12/2024 10:20:26 AM

[EventId:202412301020_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2024 10:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 30 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1020 hrs on 30 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122553NON-CONFORMANCE29/12/2024 08:45:26 AM

NON-CONFORMANCE Region NSW1 Sunday, 29 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 28 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WLWLSF1
Duration: 28/12/2024 11:40 to 29/12/2024 08:45
Amount: 147 MW
Constraint: NC-N_WLWLSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122534SETTLEMENTS RESIDUE27/12/2024 07:05:23 PM

[EventId:202412271905_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 December 2024 19:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1905 hrs on 27 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.

Refer to market notice: 122533

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1905 hrs on 27 December 2024.

This is an AEMO autogenerated Market Notice.
     
122533SETTLEMENTS RESIDUE27/12/2024 06:30:27 PM

[EventId:202412271830_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 December 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1830 hrs on 27 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122517SETTLEMENTS RESIDUE27/12/2024 03:01:56 PM

[EventId:202412271500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 December 2024 15:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 27 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 December 2024.

Refer to market notice: 122511

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 27 December 2024.

This is an AEMO autogenerated Market Notice.
     