123418SETTLEMENTS RESIDUE17/01/2025 06:00:29 PM

[EventId:202501171800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 January 2025 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 17 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Refer to market notice: 123415

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 17 January 2025.

This is an AEMO autogenerated Market Notice.
     
123415SETTLEMENTS RESIDUE17/01/2025 04:05:34 PM

[EventId:202501171605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 January 2025 16:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 17 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 17 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123413SETTLEMENTS RESIDUE17/01/2025 03:31:26 PM

[EventId:202501171530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 17 January 2025 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 17 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Refer to market notice: 123405

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 17 January 2025.

This is an AEMO autogenerated Market Notice.
     
123408MARKET INTERVENTION17/01/2025 02:52:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123385

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123407MARKET INTERVENTION17/01/2025 02:50:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123384

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123405SETTLEMENTS RESIDUE17/01/2025 01:10:24 PM

[EventId:202501171310_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 17 January 2025 13:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1310 hrs on 17 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 17 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1310 hrs on 17 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123403GENERAL NOTICE17/01/2025 10:51:11 AM

NEM Local Temperature Alerts for SA, VIC from 17 Jan 2025 to 21 Jan 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 19th Jan

VIC
Mildura Ap (39+ Deg C): 20th Jan, 21st Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123400GENERAL NOTICE16/01/2025 10:15:45 PM

Network Augmentation Commissioned - Vic Region - 16/01/2025

AEMO ELECTRICITY MARKET NOTICE


Network Augmentation Commissioned - Vic Region - 16/01/2025

At 2128 hrs 16/01/2025, the Koorangie 220 kV Terminal Station has been cut in to the existing Kerang - Wemen 220 kV transmission line resulting in the following network augmentations being commissioned:

Koorangie 220 kV Terminal Station
Koorangie - Wemen 220 kV transmission line
Kerang - Koorangie 220 kV transmission line

Manager NEM Real Time Operations
     
123385MARKET INTERVENTION16/01/2025 04:57:24 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123293

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/01/2025.

The direction update is issued at 1700 hrs 16/01/2025.

Manager NEM Real Time Operations
     