122417SETTLEMENTS RESIDUE22/12/2024 06:00:29 PM

[EventId:202412221800_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2024 18:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 22 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.

Refer to market notice: 122412

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1800 hrs on 22 December 2024.

This is an AEMO autogenerated Market Notice.
     
122412SETTLEMENTS RESIDUE22/12/2024 04:05:24 PM

[EventId:202412221605_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2024 16:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 22 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1605 hrs on 22 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122408MARKET INTERVENTION22/12/2024 04:01:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122373

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122407MARKET INTERVENTION22/12/2024 04:00:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122372

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122405MINIMUM SYSTEM LOAD22/12/2024 02:33:38 PM

Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 22/12/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual Minimum System Load (MSL) MSL1 event in the VIC Region on 22/12/2024.

Cancellation - Actual MSL1- VIC Region at 1430 hrs 22/12/2024.

Refer to Market Notice 122399for MSL1.

Manager NEM Real Time Operations
     
122399MINIMUM SYSTEM LOAD22/12/2024 11:16:27 AM

Actual Minimum System Load MSL1 condition in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE
Actual Minimum System Load MSL1 condition in the VIC Region on 22/12/2024

Update to Market Notice 122377 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.

Minimum regional demand is forecast to be 1409 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1760 MW
- MSL2 - 1260 MW
- MSL3 - 760 MW

The regional demand is below the MSL1 threshold. The actual MSL1 condition is forecast to exist until 1430 hrs.

Manager NEM Real Time Operations
     
122396SETTLEMENTS RESIDUE22/12/2024 10:20:34 AM

[EventId:202412221020_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 December 2024 10:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1020 hrs on 22 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.

Refer to market notice: 122392

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1020 hrs on 22 December 2024.

This is an AEMO autogenerated Market Notice.
     
122395MINIMUM SYSTEM LOAD22/12/2024 10:21:55 AM

Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.

Cancellation - Forecast MSL2- VIC Region at 1015 hrs 22/12/2024.

Refer to Market Notice 122385 for MSL2.

Manager NEM Real Time Operations
     
122392SETTLEMENTS RESIDUE22/12/2024 07:40:25 AM

[EventId:202412220740_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 December 2024 07:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0740 hrs on 22 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0740 hrs on 22 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     