125222SETTLEMENTS RESIDUE03/03/2025 02:00:28 PM

[EventId:202503031400_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 03 March 2025 14:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1400 hrs on 3 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 March 2025.

Refer to market notice: 125220

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1400 hrs on 3 March 2025.

This is an AEMO autogenerated Market Notice.
     
125220SETTLEMENTS RESIDUE03/03/2025 01:05:23 PM

[EventId:202503031305_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 03 March 2025 13:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1305 hrs on 3 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1305 hrs on 3 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125218SETTLEMENTS RESIDUE03/03/2025 11:00:25 AM

[EventId:202503031100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 March 2025 11:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 3 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2025.

Refer to market notice: 125216

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 3 March 2025.

This is an AEMO autogenerated Market Notice.
     
125217SETTLEMENTS RESIDUE03/03/2025 11:00:28 AM

[EventId:202503031100_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 03 March 2025 11:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 3 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 March 2025.

Refer to market notice: 125215

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1100 hrs on 3 March 2025.

This is an AEMO autogenerated Market Notice.
     
125216SETTLEMENTS RESIDUE03/03/2025 10:10:31 AM

[EventId:202503031010_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 March 2025 10:10

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 3 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1010 hrs on 3 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125215SETTLEMENTS RESIDUE03/03/2025 09:35:22 AM

[EventId:202503030935_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 03 March 2025 09:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0935 hrs on 3 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 3 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0935 hrs on 3 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125214SETTLEMENTS RESIDUE02/03/2025 04:30:25 PM

[EventId:202503021630_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 02 March 2025 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 2 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 March 2025.

Refer to market notice: 125213

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1630 hrs on 2 March 2025.

This is an AEMO autogenerated Market Notice.
     
125213SETTLEMENTS RESIDUE02/03/2025 03:35:22 PM

[EventId:202503021535_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 02 March 2025 15:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1535 hrs on 2 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 2 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1535 hrs on 2 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125202PRICES SUBJECT TO REVIEW02/03/2025 01:00:21 PM

[EventId:202503021305_review] Prices for interval 02-Mar-2025 13:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 2 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Mar-2025 13:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs