Market Notices

125251NON-CONFORMANCE04/03/2025 12:00:17 PM

NON-CONFORMANCE Region NSW1 Tuesday, 4 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 4 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 04/03/2025 11:55 to 04/03/2025 12:00
Amount: -33 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125250SETTLEMENTS RESIDUE04/03/2025 11:05:26 AM

[EventId:202503041105_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 March 2025 11:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 4 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1105 hrs on 4 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125249MARKET SYSTEMS04/03/2025 10:58:55 AM

CHG0101704 - As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane

Change Number: CHG0101704

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Business to Business data exchange
Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.
Change Start Date & Time: 04/03/2025 08:00:00
Change End Date & Time: 06/03/2025 18:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: This is the Inactive Production environment, there is no impact for external participants.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125248MARKET SYSTEMS04/03/2025 10:52:24 AM

Completed - CHG0101364 - A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0101364

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
125247MARKET SYSTEMS04/03/2025 10:49:14 AM

CHG0100544 - MSATS - CATS Production Site Transfer Brisbane to Norwest

Change Number: CHG0100544

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - CATS Production Site Transfer Brisbane to Norwest

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
125229SETTLEMENTS RESIDUE03/03/2025 05:30:38 PM

[EventId:202503031730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 March 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2025.

Refer to market notice: 125226

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 3 March 2025.

This is an AEMO autogenerated Market Notice.
     
125228SETTLEMENTS RESIDUE03/03/2025 05:30:30 PM

[EventId:202503031730_NRM_NSW1_QLD1_stopped] NEGRES CONSTRAINT NRM_NSW1_QLD1 ceased operating from 03 March 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 March 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 3 March 2025.

Refer to market notice: 125227

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to QLD directional interconnector.

The negative residue constraint NRM_NSW1_QLD1 ceased operating at 1730 hrs on 3 March 2025.

This is an AEMO autogenerated Market Notice.
     
125227SETTLEMENTS RESIDUE03/03/2025 04:45:49 PM

[EventId:202503031645_NRM_NSW1_QLD1_started] NEGRES CONSTRAINT NRM_NSW1_QLD1 started operating from 03 March 2025 16:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 3 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to QLD - 3 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to QLD directional interconnector.

The negative residue constraint set NRM_NSW1_QLD1 commenced operating from 1645 hrs on 3 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125226SETTLEMENTS RESIDUE03/03/2025 04:00:31 PM

[EventId:202503031600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 March 2025 16:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 3 March 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 March 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 3 March 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     