Cancellation - AEMO Intervention Event - SA region 20/01/2025
Cancellation - AEMO Intervention Event - SA region 20/01/2025
Refer to Market Notice 123506
The AEMO Intervention Event and all associated directions are cancelled from 1200 hrs on 26/01/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123733
Direction is cancelled from: 1200 hrs 26/01/2025
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123709
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1200 hrs 26/01/2025.
The direction update is issued at 0900 hrs 26/01/2025.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 27/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 123672
Direction is cancelled from: 0400 hrs 26/01/2025
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer AEMO Electricity Participant Notice 123674
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1400 hrs 26/01/2025.
The direction update is issued at 1600 hrs 25/01/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 25 January 2025
NON-CONFORMANCE QLD1 Region Saturday, 25 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YARANSF1
Duration: 25/01/2025 12:40 to 25/01/2025 13:10
Amount: 37 MW
Constraint: NC-Q_YARANSF1
Auto-generated on behalf of Manager NEM Real Time Operations
QNI Minor testing (NSW to Qld) 25th January 2025 for flows from NSW to Qld up to 850 MW
Refer to market notice 117923
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Saturday 25th January 2025 from 1330 to 1530hrs.
This test includes switching of transmission lines in New South Wales and/or Queensland regions.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123623
Direction is cancelled from: 1730 hrs 24/01/2025
Manager NEM Real Time Operations