[EventId:202412301435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 30 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 30 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load MSL1 condition in the VIC region on 01/01/2025
Update to Market Notice 122490 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
MSL1 - 1560 MW
MSL2 - 1060 MW
MSL3 - 560 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1030 hrs to 1430 hrs 01/01/2025. Minimum regional demand is forecast to be 1264 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1500 hrs to 1700 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1142 MW.
2. From 1730 hrs to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1328 MW.
AEMO Operations
[EventId:202412301330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 30 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Refer to market notice: 122579
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 30 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412301020_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2024 10:20
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 30 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1020 hrs on 30 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Sunday, 29 December 2024
NON-CONFORMANCE NSW1 Region Saturday, 28 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WLWLSF1
Duration: 28/12/2024 11:40 to 29/12/2024 08:45
Amount: 147 MW
Constraint: NC-N_WLWLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412271905_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 December 2024 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 27 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.
Refer to market notice: 122533
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1905 hrs on 27 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412271830_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 December 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1830 hrs on 27 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412271500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 December 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 27 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 December 2024.
Refer to market notice: 122511
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 27 December 2024.