Inter-regional transfer limit variation - Directlink- NSW region - 13/02/2025
Inter-regional transfer limit variation - No.2 Leg of Directlink - NSW region - 13/02/2025
A planned outage of the No.2 Leg of Directlink in the NSW region was scheduled from 1517 hrs 30/01/2025 to 1700 hrs 20/02/2025.
The outage has been completed and the No.2 Leg of Directlink returned to service at 1312 hrs 13/02/2025
Constraint set(s) revoked: N-X_MBTE_2
Manager NEM Real Time Operations
Fast Frequency Response Market - Removal of R1 FCAS dispatch cap from 17th February 2025
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 17th February AEMO will remove the cap on dispatch of Very Fast Raise (R1) Contingency FCAS.
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equations will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 524 MW
The minimum capacity reserve available is 470 MW
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 12 Feb 2025 to 16 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 12th Feb
Clare High School (39+ Deg C): 12th Feb
Mt Gambier Ap (39+ Deg C): 12th Feb
Port Augusta Ap (39+ Deg C): 12th Feb
VIC
Mildura Ap (39+ Deg C): 12th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-regional transfer limit variation - Armidale No 1 SVC- NSW region - 11/02/2025
Inter-regional transfer limit variation - Armidale No 1 SVC - NSW region - 11/02/2025
At 2315 hrs 11/02/2025 there was an unplanned outage of Armidale No 1 SVC.
The following constraint set(s) invoked at 2325 hrs 11/02/2025
N-AR_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025
Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025
At 1750 hrs 11/02/2025 there was a short notice outage of Yass Overload Control Scheme.
The following constraint set(s) invoked at 1750 hrs: N-YSWG_SCHEME
This constraint set(s) contains equations with the following interconnectors on the LHS,
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .
The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
Referring to Market Notice 124466.
The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.
Constraint set revoked: CA_SYDS_56BD5936
Manager NEM Real Time Operations