Market Notices

122841RESERVE NOTICE04/01/2025 06:56:10 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122832 has been updated at 1845 hrs 04/01/2025 to the following:

From 1430 hrs 06/01/2025 to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 1114 MW.
The minimum capacity reserve available is 700 MW.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122832RESERVE NOTICE04/01/2025 03:44:54 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122826 has been updated at 1530 hrs 04/01/2025 to the following:

[1.] From 1500 hrs 06/01/2025 to 1600 hrs 06/01/2025.
The forecast capacity reserve requirement is 882 MW.
The minimum capacity reserve available is 700 MW.

[2.] From 1630 hrs 06/01/2025 to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 963 MW.
The minimum capacity reserve available is 650 MW.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122826RESERVE NOTICE04/01/2025 04:38:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122823 has been updated at 0430 hrs 04/01/2025 to the following:

From 1430 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1228 MW.
The minimum capacity reserve available is 603 MW.
AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122823RESERVE NOTICE03/01/2025 09:36:20 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122818 has been updated at 2130 hrs 03/01/2025 to the following:

From 1430 hrs 06/01/2025 to 2030 hrs 06/01/2025.
The forecast capacity reserve requirement is 1336 MW.
The minimum capacity reserve available is 535 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122818RESERVE NOTICE03/01/2025 06:38:11 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122810 has been updated at 1830 hrs 03/01/2025 to the following:

From 1430 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 1298 MW.
The minimum capacity reserve available is 427 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122810RESERVE NOTICE03/01/2025 04:40:51 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122772 has been updated at 1630 hrs 03/01/2025 to the following:

[1.] From 1430 hrs 06/01/2025 to 1600 hrs 06/01/2025.
The forecast capacity reserve requirement is 1149 MW.
The minimum capacity reserve available is 700 MW.

[2.] From 1630 hrs 06/01/2025 to 1830 hrs 06/01/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 488 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
122785PRICES SUBJECT TO REVIEW03/01/2025 09:55:26 AM

[EventId:202501031000_review] Prices for interval 03-Jan-2025 10:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0955 hrs on 3 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 03-Jan-2025 10:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122784PRICES SUBJECT TO REVIEW03/01/2025 09:50:27 AM

[EventId:202501030955_review] Prices for interval 03-Jan-2025 09:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0950 hrs on 3 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 03-Jan-2025 09:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
122783PRICES SUBJECT TO REVIEW03/01/2025 09:45:15 AM

[EventId:202501030950_review] Prices for interval 03-Jan-2025 09:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0945 hrs on 3 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 03-Jan-2025 09:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm