PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/05/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 30/05/2025 to 1800 hrs 30/05/2025.
The forecast capacity reserve requirement is 1738 MW.
The minimum capacity reserve available is 1669 MW.
Manager NEM Real Time Operations
Fast Frequency Response Market - Local dispatch of Very Fast Contingency FCAS in SA and QLD
Following a review of the operation of the Very Fast FCAS market, AEMO will commence local dispatch of Very Fast FCAS in the South Australia (SA) and Queensland (QLD) regions from 10th June 2025, during periods where islanding of the region is considered credible.
An initial dispatch cap of 100 MW will apply in the SA region, and 20 MW in the QLD region. These caps will be reviewed and updated regularly.
From the same date, AEMO will also dispatch Very Fast FCAS in the QLD region when an actual islanding event occurs. In this scenario, no dispatch cap will apply.
Dispatch of Very Fast FCAS in the SA region under actual islanding conditions commenced in 2024. Refer to Market Notice 117238 for further details.
For more information on the Fast Frequency Response (FFR) initiative, please visit:
https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025
Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025
At 1750 hrs 28/05/2025 there was a short notice outage of Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines.
The following constraint set(s) invoked at 1745 hrs 28/05/2025
N-ARDM_8C
N-X_8C+DM+TW_SVC
and the following constraint set(s) invoked at 1750 hrs 28/05/2025
I-BCDM_ONE
N-X_8L+DM+TW_SVC
These constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Brinkworth - Templers West 275 kV line - SA region - 27/05/2025
Inter-regional transfer limit variation - Brinkworth - Templers West 275 kV line - SA region - 27/05/2025
At 0337 hrs 27/05/2025 there was an unplanned outage of Brinkworth - Templers West 275 kV line.
The following constraint set(s) invoked at 0340 hrs 27/05/2025
S-BRTW
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Woolooga No. 4 275 kV SVC - QLD region - 26/05/2025
Inter-regional transfer limit variation - Woolooga No. 4 275 kV SVC - QLD region - 26/05/2025
At 0808 hrs 26/05/2025 there was an unplanned outage of Woolooga No. 4 275 kV SVC.
The following constraint set(s) invoked at 0815 hrs 26/05/2025
Q-WO_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Black Range No.1 275 kV Series Capacitor - SA region - 18/05/2025
Inter-regional transfer limit variation - Black Range No.1 275 kV Series Capacitor - SA region - 18/05/2025
At 0916 hrs 18/05/2025 there was an unplanned outage of Black Range No.1 275 kV Series Capacitor.
The following constraint set(s) invoked at 0955 hrs 18/05/2025
S-BC_CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 15/05/2025
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127067 is cancelled at 1410 hrs 15/05/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 16/05/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 16/05/2025 to 1800 hrs 16/05/2025.
The forecast capacity reserve requirement is 1216 MW.
The minimum capacity reserve available is 1201 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/05/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 127043 is cancelled at 1740 hrs 13/05/2025.
Manager NEM Real Time Operations