Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025
At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.
The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0101257 - Frequency Performance Payments Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments Release
Change Start Date & Time: 19/03/2025 08:00:00
Change End Date & Time: 20/03/2025 16:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Delivery of Frequency Performance Payments (FPP) calculation results via the participant data model may be periodically delayed during the change window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025
Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025
At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.
The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025
Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025
At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.
The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
CHG0101808 - Pre-production EMMS database Maintainence activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
CHG0101808 - Pre-production EMMS database Maintainence activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
CHG0101876 - Pre-Prod eMDM Hotfix Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Hotfix Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0101704 - As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisban
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025
Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025
An unplanned outage of Directlink Cables 1 and 2 in the NSW region was scheduled to return to service at 1700 hrs 12/03/2025.
The outage has been completed and Directlink Cables 1 and 2 returned to service at 1350 hrs 12/03/2025
Constraint set(s) revoked: N-X_MBTE_3
Manager NEM Real Time Operations