Inter-regional transfer limit variation - Bundey to Buronga (6F) 330kV line - NSW region - 24/01/2025
Inter-regional transfer limit variation - Bundey to Buronga (6F) 330kV line - NSW region - 24/01/2025
A planned outage of Bundey to Buronga (6F) 330kV line in the NSW region was scheduled from 1931 hrs 21/01/2025 to 1900 hrs 25/01/2025.
The outage has been completed and Bundey to Buronga (6F) 330kV line returned to service at 0900 hrs 24/01/2025
Constraint set(s) revoked: I-BDBU_ONE
Manager NEM Real Time Operations
CHG0100766 | Completed | Production | Planned Maintenance to Brisbane ISE Server
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Brisbane ISE Server
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the Qld Region on 24/01/2025
The Forecast LOR2 condition in the Qld region advised in AEMO Electricity Market Notice No. 123636 is cancelled at 2340 hrs 23/01/2025
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123625 has been updated at 1700 hrs to the following:
[1.] From 1800 hrs 24/01/2025 to 1900 hrs 24/01/2025.
The forecast capacity reserve requirement is 813 MW.
The minimum capacity reserve available is 751 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lismore No.1 132 kV SVC - NSW region - 23/01/2025
Inter-regional transfer limit variation - Lismore No.1 132 kV SVC - NSW region - 23/01/2025
A planned outage of Lismore No.1 132 kV SVC in the NSW region was scheduled from 2200 hrs 22/01/2025 to 1600 hrs 24/01/2025.
The outage has been completed and Lismore No.1 132 kV SVC returned to service at 1631 hrs 23/01/2025
Constraint set(s) revoked: N-LS_VC1
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 816 MW.
The minimum capacity reserve available is 572 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123619 is cancelled at 1000 hrs 23/01/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 863 MW.
The minimum capacity reserve available is 825 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025
Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123589 is cancelled at 2015 hrs 22/01/2025.