Market Notices

123986MARKET INTERVENTION01/02/2025 03:48:29 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 123979

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 02/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 01/02/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
123985MARKET INTERVENTION01/02/2025 04:01:19 PM

Cancellation - AEMO Intervention Event - SA region 26/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 26/01/2025

Refer to Market Notice 123745

The AEMO Intervention Event and all associated directions are cancelled from 1600 hrs on 01/02/2025.


Manager NEM Real Time Operations
     
123984MARKET INTERVENTION01/02/2025 03:54:48 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123965

Direction is cancelled from: 1600 hrs 01/02/2025

Manager NEM Real Time Operations
     
123979MARKET INTERVENTION01/02/2025 07:29:01 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 02/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123966MARKET INTERVENTION01/02/2025 03:57:13 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123925

Direction is cancelled from: 0400 hrs 01/02/2025

Manager NEM Real Time Operations
     
123965MARKET INTERVENTION31/01/2025 03:59:12 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123924

PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1600 hrs 01/02/2025.

The direction update is issued at 1600 hrs 31/01/2025.

Manager NEM Real Time Operations
     
123962RESERVE NOTICE31/01/2025 03:03:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 123926 is cancelled at 1400 hrs 31/01/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
123957NON-CONFORMANCE31/01/2025 11:31:33 AM

NON-CONFORMANCE Region NSW1 Friday, 31 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 31 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123926RESERVE NOTICE30/01/2025 02:45:47 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

From 1630 hrs to 1830 hrs 03/02/2025.
The forecast capacity reserve requirement is 1130 MW.
The minimum capacity reserve available is 1022 MW.

AEMO Operations
     