NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025
NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502080755_review] Prices for interval 08-Feb-2025 07:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0750 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502080750_review] Prices for interval 08-Feb-2025 07:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0745 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502080745_review] Prices for interval 08-Feb-2025 07:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0740 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502080740_review] Prices for interval 08-Feb-2025 07:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502080735_review] Prices for interval 08-Feb-2025 07:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0730 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502080730_review] Prices for interval 08-Feb-2025 07:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0725 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202502080725_review] Prices for interval 08-Feb-2025 07:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 0720 hrs on 8 February 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Feb-2025 07:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV
Cancellation time: 08/02/2025 06:24
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 124323
Auto-generated on behalf of Manager NEM Real Time Operations