The Consultation Process
The consultation process is now closed. Relevant dates are outlined below.
Process Stage | Date |
---|---|
Publication of Procedure Change Proposal: GPS Compliance Tests and Generator Monitoring Plans |
23 September 2024 |
APCWG forum |
25 September 2024 |
Closing date for submissions on Procedure Change Proposal |
21 October 2024 |
Publication of Procedure Change Report |
28 October 2024 |
Proposed commencement of amended Procedure |
29 October 2024 |
Procedure Change Proposal
Wholesale Electricity Market Rules – Clause 2.10
Date of Notice: 23 September 2024
Matter under Consultation
AEMO initiated this Procedure Change Proposal to amend the WEM Procedure GPS Compliance Tests and Generator Monitoring Plans to:
- update Market Information provisions to be consistent with the amended Chapter 10 provisions that commenced on 1 October 2023.
- update date references from Business Days to calendar days (days) to ensure consistency with the WEM Procedure: Commissioning Tests.
- require that a separate Generator Monitoring Plan Template be submitted for each Registered Facility that contains a Generating System with Registered Generator Performance Standards, to cover prospective rule changes that may provide for registration of multiple Separate Facilities behind a connection point.
- incorporate minor amendments to improve readability and clarity, including the addition of an explanatory process flow chart, and to fix minor errors.
AEMO sought comment and feedback on:
- whether the proposed changes to the Procedure effectively implement AEMO’s intended outcomes and give effect to the Amending Rules.
- whether stakeholders believe there are any other relevant issues that have not been considered.
Procedure Change Proposal documents
-
23/09/2024
Call for Submissions on Procedure Change Proposal AEPC_2024_11
177.76 KB -
23/09/2024
Procedure Change Proposal AEPC_2024_11
142.52 KB -
23/09/2024
Proposed amendment version WEM Procedure: GPS Compliance Tests and Generator Monitoring Plans
566.74 KB -
23/09/2024
Proposed amendment version WEM Procedure: GPS Compliance Tests and Generator Monitoring Plans (marked up)
405.79 KB
Invitation to Make Submissions
AEMO invited written submissions on the Procedure Change Proposal, including any alternative or additional proposals to improve the procedure/s or better meet the Wholesale Market Objectives in section 122(2) of the Electricity Industry Act 2004 (and clause 1.2.1 of the WEM Rules).
Respondents were asked to identify any parts of their submission that they wished to remain confidential, explaining why. AEMO noted that it, following consultation with the respondent, may still publish that information if it does not consider it to be confidential in accordance with the WEM Rules.
Meetings
Before the closing date for submissions, stakeholders were advised that they may request a meeting with AEMO to discuss the issues and proposed changes raised in the Procedure Change Proposal, stating why they considered a meeting is necessary or desirable.
AEMO will generally make details of matters discussed at a meeting available to other stakeholders, and may publish those details.
Closing Date and Time
Stakeholders were advised that submissions in response to this Procedure Change Proposal should be sent by email to WA.Marketdevelopment@aemo.com.au, to reach AEMO by 5.00 pm (AWST) on 21 October 2024.
All submissions must be in electronic format (pdf or Microsoft Word). Submissions should use the Procedure Change Submission form available on this page.
AEMO is not obliged to consider submissions received after the closing date and time. Any late submissions should explain the reason for delay and the detriment to you if AEMO does not consider your submission.
Publication
All submissions are published on AEMO’s website. Confidential information is not published, other than as specified above.
Submissions
No submissions received.