Transgrid and Endeavour Energy PSCR: Meeting demand growth in the Western Sydney Aerotropolis ‘Priority Growth Area’

07/05/2024
Market Network Service Provider
StageProject Specification Consultation Report
ConvenorAEMO NSP
Initiated07/05/2024
Accepting submissions?Yes
Submissions close05/08/2024

Transgrid has recently published a Project Specification Consultation Report (PSCR) for meeting demand growth in the Western Sydney Aerotropolis ‘Priority Growth Area’. This PSCR has been prepared in conjunction with Endeavour Energy (as the relevant distribution network service provider).

Transgrid and Endeavour Energy have determined that expected demand increases sourced from Aerotropolis precinct developments will result in power flows exceeding the capacity of the Macarthur 132 kV transmission Bulk Supply Point (BSP) from 2026/27 under system normal conditions. This will require load shedding under both system normal and contingency conditions at the Macarthur 132 kV BSP after Endeavour Energy completes the first phase of its current supply network upgrades in the area.

Transgrid and Endeavour Energy have identified an opportunity to improve network supply capacity to the Aerotropolis precinct. This will provide significant net market benefits to participants in the National Electricity Market (NEM) by eliminating the need for load shedding. Consequently, this RIT-T is considered to be a ‘market benefits’ driven RIT-T (i.e., as opposed to a ‘reliability corrective action’).

The PSCR presents two feasible options that, from a technical, commercial, and project delivery perspective, can be implemented in sufficient time to meet the identified need. Option 1 is centred on the introduction of a new BSP next to the Kemps Creek substation. Option 2 is focused on the introduction of a new Airport South BSP supplied from cut-in to line 39. 
Option 1 is currently forecast to have a total capital cost of $132.8m ($2023-24). Option 2 is forecast to have a total capital cost of $257.7m ($2023-24). 

Transgrid and Endeavour Energy welcome written submissions on materials contained in this PSCR. Submissions are due on 5 August 2024.

The next formal stage of this RIT-T is the publication of the Project Assessment Draft Report (PADR). The PADR will include the full quantitative analysis of the credible options and is anticipated to be published in late 2024.

In accordance with the requirements of the Rules, a summary of the PSCR is made available on the AEMO website. A copy of the PSCR can be obtained from Transgrid’s website, Endeavour Energy’s website, or by emailing regulatory.consultation@transgrid.com.au.

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm