Proposed Timeline
-
IIR publication date27 February 2024
-
IIR consultation submissions due19 March 2024
-
Decision publication date28 March 2024
-
Effective Date of Procedures22 April 2024
AEMO is removing the Rosalind Park Custody Transfer Point from the STTM procedures section 2.2(d), described as:
custody transfer point 4: the connection between the respective pipelines identified in Pipeline Licence No. 30 (Rosalind Park CSM) and Pipeline Licence No. 1 (Wilton to Horsley Park) issued under the Pipelines Act 1967 of New South Wales, being the Rosalind Park Receipt Point located at chainage KP 15.3 of the Wilton to Horsley Park natural gas pipeline.
AEMO is undertaking an expedited Procedure change under NGR135EF to implement the STTM Procedure change as the Procedure change is considered to be non-material being only the removal of a custody transfer point.
For further information please contact GWCF_correspondence@aemo.com.au.