TransGrid Project Assessment Conclusions Report: Managing safety and environment risks on Line 3W (Kangaroo Valley – Capital Wind Farm)

24/01/2020
Market Network Service Provider, National Electricity Market
StageProject Assessment Conclusions Report
ConvenorAEMO NSP
Initiated24/01/2020
Accepting submissions?No

TransGrid has recently published a Project Assessment Conclusions Report for managing safety and environmental risks on Line 3W (Kangaroo Valley – Capital Wind Farm). 

Constructed in 1972, the 130 km single circuit 330 kV transmission line is comprised of 296 steel tower structures between Capital Wind Farm and Kangaroo Valley 330 kV switching stations. Line 3W forms a key link between Canberra and Wollongong and enables the transmission of electricity from generators in the area including Capital Wind Farm, Woodlawn Wind Farm, Kangaroo Valley Pumping and Power Station, and Bundeela Pumping and Power Station to the NEM. 

A significant proportion of the steel transmission structures of Line 3W are impacted by various levels of deterioration and corrosion. The affected components include tower steelwork, foundations and earthing, insulators, conductor fittings, earthwire and associated fittings. This greatly increases the likelihood of transmission structure failures, conductor drop, and subsequent bushfire and safety risks. 

TransGrid considered three credible options that would meet the identified need from a technological and project delivery perspective. Refurbishment of the line remains the most economical and preferred option at this stage of the RIT-T process.

No submissions were received in response to the Project Specification Consultation Report (PSCR) during the consultation period which closed on 21 January 2020. No additional credible options that could deliver a material economic benefit were identified throughout the process and the outcomes of the economic analysis contained in the PSCR are maintained in this PACR.

The works for the preferred option are to be completed by 2021/22. The estimated capital cost of the proposed preferred option is $14.5 million ± 25%. TransGrid is the proponent of the proposed network project.

In accordance with the requirements of the National Electricity Rules, a summary of the PACR is made available on the AEMO website. A copy of the PACR can be obtained from TransGrid’s website on the Regulatory Investment Tests page  or by emailing RIT-TConsultations@TransGrid.com.au.

X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm